WORKING CAPITAL QUESTION While preparing a project report on behalf of a client you have collected the following facts Estimate the net working capital required for that project Add 10% to your

WORKING CAPITAL: QUESTION While preparing a project report on behalf of a client you have collected the following facts. Estimate the net working capital required for that project. Add 10% to your computed figure to allow contingencies. Estimated cost per unit of production is: Amount ($) Raw material 80 Direct Labor 30 Overheads 60 Total Cost 170

 

May 02 2020 View more View Less

Answer (Solved)