The NPV for project A is $100,000, if the cost of capital is 6%, calculate the EAC over its three-year life

The NPV for project A is $100,000, if the cost of capital is 6%, calculate the EAC over its three-year life. A. 50,000 B. 43,000 C. 37,411 D. 57,619