For Week 1, the budgeted labour hours for normal activity are 5,000 hours. The budgeted fixed costis £15,000. The fixed overhead cost rate is calculated on the basis of budgeted cost and budgeted normal activity. At the end ofthe week it is found that only 4,000 hours were worked in practice. What is the amount of fixed overhead applied to jobs in Week 1?

(A) £3,000

(B) £12,000

(C) £15,000

(D) £18,000