Soalan 1/Question 1 (8 markah/marks) (a) Berdasarkan jadual di bawah. Based on following table, Pendahulu Predecessor(s) Aktiviti Activity A B с D E F G H Tempoh (hari) Duration (days) 3 6 7 5 13 8 11

Soalan 1/Question 1 (8 markah/marks) (a) Berdasarkan jadual di bawah. Based on following table, Pendahulu Predecessor(s) Aktiviti Activity A B с D E F G H Tempoh (hari) Duration (days) 3 6 7 5 13 8 11 6 A A A B.C CD DF GE 1. Draw a network diagram representing the information in the above table. 2. In a table form, calculate the Earliest Start, Earliest Finish, Latest Start and Latest Finish for the project ES EF LS LF Slack Activity A B с D E F G H i. Calculate the total duration of the project. ii. Determine the critical path of the project.