Preparing a financial budget-schedule of cash payments Barnes Company budgeted direct materials purchases of $191,990 in January and $138,610 in February. Assume Barnes pays for direct materials purchases 60% in the month of purchase and 40% in the month after purchase. The Accounts Payable balance on January 1 is $75,000. Prepare a schedule of cash payments for purchases for January and February. Round to the nearest dollar.

 