P12-16 MacIntyre Fabrications, Ltd., of Aberdeen,
Scotland, has recently begun a continuous improvement campaign in conjunction
with a move toward Lean Production. Management has developed new performance
measures as part of this campaign. The following operating data have been
gathered over the last four months:
Month
1 2
3
4
Throughput time . . . . . . . . . . . . . . . . . .
. . . . ? ?
?
?
Manufacturing cycle efficiency . . . . . . . . . .
. ?
?
?
?
Delivery cycle time . . . . . . . . . . . . . . . .
. . . . ? ?
?
?
Percentage of on-time deliveries . . . . . . . . .
72% 73% 78%
85%
Total sales (units) . . . . . . . . . . . . . . . .
. . . . . 10,540
10,570
10,550
10,490
Management would like to know the company’s
throughput time, manufacturing cycle efficiency, and delivery cycle time. The
data to compute these measures have been gathered and appear below:
Month
1 2
3
4
Move time per unit, in days . . . . . . . . . . . .
0.5 0.5
0.4 0.5
Process time per unit, in days . . . . . . . . . .
0.6 0.5
0.5 0.4
Wait time per order before start of
production, in days . . . . . . . . . . . . . . . .
9.6
8.7 5.3
4.7
Queue time per unit, in days . . . . . . . . . . .
3.6 3.6
2.6 1.7
Inspection time per unit, in days . . . . . . . .
0.7 0.7
0.4 0.3
Required:
1. For each month, compute the following:
a.The throughput time.
b.The manufacturing cycle efficiency (MCE).
c.The delivery cycle time.
2. Using the performance measures given in the
problem and those you computed in (1) above, identify whether the trend over
the four months is generally favorable, generally unfavorable, or mixed. What
areas apparently require improvement and how might they be improved?
3. Refer to the move time, process time, and so
forth, given for month 4.
a.Assume that in month 5 the move time, process time,
and so forth, are the same as for month 4, except that through the
implementation of Lean Production, the company is able to completely eliminate
the queue time during production. Compute the new throughput time and MCE.
b.Assume that in month 6 the move time, process time,
and so forth, are the same as for month 4, except that the company is able to
completely eliminate both the queue time during production and the inspection
time. Compute the new throughput time and MCE.
Jun 26 2020 View more View Less
Explain the symptoms and causes of job stress, and what the organization can do to alleviate it. >
May 30 2020Determine the amount of money that needs to be deposited 5 years from now to withdraw $6,000 per yearfor 7 years beginning 10 years from now if the interest rate is 8% pe...
Jun 02 2018A 0.500 ft x 0.500 ft x 0.500 ft cube of soil is subjected to a vertical compressive force of 500 lb. This force is being applied to the top of the cube. As a result of t...
Jul 11 2020If the asteroid fragment contains carbon, it may burn when entering Earth’s atmosphere. What is the most likely compound to result from this process? Which type of chemic...
May 10 2020PSY 360 Language PaperWritea 1,050- to 1,400-word paper in which you examine language as it relates to cognition. Address the following:· Definelanguageandlexicon· Evalua...
Aug 09 20201. What are McDonald s Canada core brand values? Have these changed over the years? 2. McDonald s did very well during the recession in the late 2000s. With the economy t...
Jul 24 2020A firm's production function C is given by C (q) = 0:5q 2+2q 1 2 +18, where q is the level of output.(i) Calculate marginal costs(ii) If all fixed costs are sunk, an...
Apr 23 2020On January 1, Evangel Company issued 9% bonds in the face amount of $100,000, which mature in 5 years. The bonds were issued for $96,207 to yield 10%, resulting in a bond...
Mar 20 2020One kilogram of air as an ideal gas executes a Carnot powercycle having a thermal efficiency of 50%. The heat transfer to theair during the isothermal expansion is50 kJ. ...
May 05 2020Compensable factors are concrete terms relating to the necessary education, skill, and work experience for compensation at a particular level.118) A job hierarchy lists j...
Mar 13 2020