Marked out of 1.00 P Flag question If the Profitability Index of a project is 0.7 and the initial outlay = 5000. Then the present value of the project equals :- Select one: a

Marked out of 1.00 P Flag question If the Profitability Index of a project is 0.7 and the initial outlay = 5000. Then the present value of the project equals :- Select one: a. 3500 b. 5000 C. 7142 d. None of the above