Labor Variances Verde Company produces wheels for bicycles During the year 660000 wheels were produced The actual labor used was 360000 hours at $9 50 per hour Verde has the following labor

Labor Variances Verde Company produces wheels for bicycles. During the year, 660,000 wheels were produced. The actual labor used was 360,000 hours at $9.50 per hour. Verde has the following labor standard: 0.5 hour at $10.

Required:

1. Compute the labor rate variance.

2. Compute the labor efficiency variance.