Klassen Toy Company Inc assembles two parts parts 1 and 2 Part 1 is first processed at workstation A for 15 minutes per unit and then processed at workstation B for 10 minutes per unit

Klassen Toy Company, Inc., assembles two parts ( parts 1 and 2 ): Part 1 is first processed at workstation A for 15 minutes per unit and then processed at workstation B for 10 minutes per unit. Part 2 is simultaneously processed at workstation C for 20 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D, where the two parts are assembled. The time at workstation D is 15 minutes.

a) What is the bottleneck of this process?

b) What is the hourly capacity of the process?