Create an Account

Already have account?

Forgot Your Password ?

Home / Questions / In the Microsoft Excel, add a new worksheet called “Earned Value.” with the exception of t...

In the Microsoft Excel, add a new worksheet called “Earned Value.” with the exception of the followi

In the Microsoft Excel, add a new worksheet called “Earned Value.” with the exception of the following:Instead of BAC=$200,000, use the total project cost for your project.Instead of PV=$100,000, use the Week 16 Cumulative Cost from your Project Cash Flow Report generated above.Assume that you have completed three months of the project. The BAC was $200,000 for this six-month project. You can also make the following assumptions:PV ¼ $120,000EV ¼ $100,000AC ¼ $90,000a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?d. Use the SPI to estimate how long it will take to finish this project.e. Sketch an earned value chart using the preceding information. See Figure 7-5 as a guide.Term FormulaEarned value (EV) EV ¼ PV to date * RPCost variance (CV) CV ¼ EV _ ACSchedule variance (SV) SV ¼ EV _ PVCost performance index (CPI) CPI ¼ EV/ACSchedule performance index (SPI) SPI ¼ EV/PVEstimate at completion (EAC) EAC ¼ BAC/CPIEstimated time to complete Original time estimate/SPI

 

Apr 27 2020 View more View Less

Answer (Solved)

question Subscribe To Get Solution

Related Questions