In spring 2012, Lowell Engineering Company signed an $120million contract with the city of Chelmsford, to construct a newcity hall. Lowell Inc. expects to construct the building within twoyears and incur expenses of $70 million. The city of Chelmsfordpaid $40 million when the contract was signed, $60 million withinthe next six months, and the final $20 million exactly one yearfrom the signing of the contract. Lowell Inc. incurred $35 millionin costs during 2012 and rest in 2013 to complete the contract ontime. Using the percentage-of-completion method how much revenueshould Lowell Inc. recognize in 2012?