In a PERT network, the sequence of events and activities requiring the longest period

In a PERT network, the sequence of events and activities requiring the longest period

 In a PERT network, the sequence of events and activities requiring the longest period of time tocomplete is

[A]Called the network

[B]Indicated by thin arrows

[C]The path that managers avoid

[D]The critical path