EXERCISE 11 3 Measures of Internal Business Process Performance LO3 Lipex Ltd of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when

EXERCISE 11–3 Measures of Internal Business Process Performance [LO3]

Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported:

 

Text Box: Inspection time . . . . . . . . . . . . . . . . . . . . .	0.5 days Process time . . . . . . . . . . . . . . . . . . . . . . .	2.8 days Wait time. . . . . . . . . . . . . . . . . . . . . . . . . .	16.0 days Queue time . . . . . . . . . . . . . . . . . . . . . . . .	4.0 days Move time . . . . . . . . . . . . . . . . . . . . . . . . .	0.7 days

 

Required:

1.       Compute the throughput time.

2.       Compute the manufacturing cycle efficiency (MCE) for the quarter.

3.       What percentage of the throughput time was spent in non–value-added activities?

4.       Compute the delivery cycle time.

5.       If by using Lean Production all queue time can be eliminated in production, what will be the new MCE?