END3760 Scheduling Project There is a 5 jobs 3 machines flow shop problem. M1 J1 J2 J3 27 12 11 8 14 M2 10 9 10 13 12 8 10 8 12 9 J4 J5 Try to develop a new heuristic methodology to solve the flow

END3760 Scheduling Project There is a 5 jobs 3 machines flow shop problem. M1 J1 J2 J3 27 12 11 8 14 M2 10 9 10 13 12 8 10 8 12 9 J4 J5 Try to develop a new heuristic methodology to solve the flow shop problem. Explain the idea of your methodology. Determine the steps of your methodology.