Home / Questions / Crash Task Time Dependency Cost Crash time cost/week a 4 11 1 110 b 5 a 8 1 65 с 6 a 9 2 7...

Crash Task Time Dependency Cost Crash time cost/week a 4 11 1 110 b 5 a 8 1 65 с 6 a 9 2 70 d 12 b, c 20 2 150 e 5 b 12 1 50 f 4 d 7 1 90 g 9 с 14 1 60 h 2 e, f, g 4 1 70 Fully crash the project, and

Crash Task Time Dependency Cost Crash time cost/week a 4 11 1 110 b 5 a 8 1 65 с 6 a 9 2 70 d 12 b, c 20 2 150 e 5 b 12 1 50 f 4 d 7 1 90 g 9 с 14 1 60 h 2 e, f, g 4 1 70 Fully crash the project, and draw crash curve using different colours. Note: • Draw all steps when crashing. • Do not print (it is handwriting assignment)

Apr 17 2021 View more View Less