Consider the following single machine-scheduling problem with weights. Job (i) 1 2. 2 3 4 5 Processing time (t) 15 4 5 14 8 Weight, wj 1 2 1 2 3 Determine the sequence, which will minimize the weighte

Consider the following single machine-scheduling problem with weights. Job (i) 1 2. 2 3 4 5 Processing time (t) 15 4 5 14 8 Weight, wj 1 2 1 2 3 Determine the sequence, which will minimize the weighted mean flow time of the above problem.
Select one: a. 3-5-2-4-1 b. 3-5-2-4-1 C. 3-5-2-1-4 O d. 5-3-2-1-4