Based on the following table, compute the following: 1- Duration of project: 2- LS (F) 3- Ef (D) = 4 - Float (A) Starts after Duration Activity 3 А 4 B 2 с А 1 D D 2 E A N F C.B 5 G G 4 Н.

Based on the following table, compute the following: 1- Duration of project: 2- LS (F) 3- Ef (D) = 4 - Float (A) Starts after Duration Activity 3 А 4 B 2 с А 1 D D 2 E A N F C.B 5 G G 4 Н.