Assume the following information for an IT project. Probability of Failure Consequences of Failure Maturity

Assume the following information for an IT project. Probability of Failure Consequences of Failure Maturity = .7 ……………………………. Cost = .9 Complexity = .7 …………………………. Schedule = .7 Dependency = .5 ………………………… Performance = .3 Client Concerns = .5 …………………….. Future Business = .5 Programmer Skill = .3 Calculate the overall risk factor for this project. Would you assess this level of risk as low, moderate, or high? Why?