A risk-averse manager is considering two projects The first project involves expanding themarket for bologna the second involves expanding the market for caviar There is a 10 per-cent chance of

A risk-averse manager is considering two projects. The first project involves expanding themarket for bologna; the second involves expanding the market for caviar. There is a 10 per-cent chance of a recession and a 90 percent chance of an economic boom. During a boom,the bologna project will lose $10,000 whereas the caviar project will earn $20,000. During arecession, the bologna project will earn $12,000 and the caviar project will lose $8,000. Ifthe alternative is earning $3,000 on a safe asset (say, a Treasury bill), what should the man-ager do? Why?