A production line at V. J. Sugumaran’s machine shop has three stations. The first station can process a unit in 10 minutes. The second station has two identical machines, each of which can process a unit in 12 minutes. (Each unit only needs to be processed on one of the two machines.) The third station can process a unit in 8 minutes. Which station is the bottleneck station?

 