Home / Questions / Thurman Brothers Construction manufactures and installs standard and custom-made cabinetry

Thurman Brothers Construction manufactures and installs standard and custom-made cabinetry

Thurman Brothers Construction manufactures and installs standard and custom-made cabinetry for residential homes. Last year, the company incurred $600,000 in overhead costs when a total of 10,000 direct labor hours were incurred. After implementing activity-based costing (ABC), the company’s accountant identified the following related information:
 

Activity

Allocation Base

Proportion of Overhead Cost

Material delivery and handling

Number of deliveries

30%

Inspections

Number of inspections

25%

Supervision

Hours of supervisor time

20%

Purchasing

Number of purchase orders

25%

 

 

 


The number of activities for standard and custom-made cabinets are as follows:
 

 

Standard

Custom-made

     

Number of deliveries

500

700

     

Number of inspections

600

400

     

Hours of supervisor time

1,000

2,000

     

Number of purchase orders

800

400

     

 

 

 

 

 

 

           


During the past year, Thurman accepted a customer order for a set of custom-made cabinets that would require the following:
 

Direct labor hours --------------------------------------------

45

 

 

Number of deliveries -----------------------------------------

4

Number of inspections ---------------------------------------

5

Hours of supervisor time ------------------------------------

2

Number of purchase orders ---------------------------------

4

 

 


Required:
 

A.

How much overhead would be applied to the job if traditional costing using direct labor hours as the cost driver were used?

 

 

B.

Using activity-based costing (ABC), what would be the overhead rate for each of the four activities?

 

 

C.

Using activity-based costing (ABC), what would be the total overhead applied to the above job?

 

 

D.

Compare the overhead applied using traditional costing to ABC costing and remark on the difference. Which one do you think is more accurate?