Home / Questions / The Alpha Beta Company produces Product A . In order to produce one unit of A 3 units of ...

The Alpha Beta Company produces Product A . In order to produce one unit of A 3 units of Part B, 3 units of Part C and 2 units of Part D are required. In order to produce Part D, 2 units of C and 4

The Alpha Beta Company produces Product A .

  • In order to produce one unit of A 3 units of Part B, 3 units of Part C and 2 units of Part D are required.
  • In order to produce Part D, 2 units of C and 4 units of E is required.
  • Lead times are 2 weeks for A and D; 3 weeks for B, C and E

      Given the following information prepare a materials requirement plan for Part C.

      Fill in the required number of tables below:

    

Item

On Hand

Scheduled Receipts

Lot size

Orders to be shipped

A

10

0

L4L

500, period 7

300, period 11

B

-

0

L4L

-

C

600

500, period 8

L4L

-

D

200

850, period 2

L4L

-

E

-

25, period 1

L4L

-

            LFL means just the required amount

           Indicate the product or part code for each table

----------

 

1

2

3

4

5

6

7

8

9

10

11

12

Gross requirements

                       

Scheduled receipts

                       

Projected on hand

                       

Net requirements

                       

Planned-order rece.

                       

lanned-order rel.

                       