Summerlin Company budgeted 4,500 pounds of material costing $5.00 per pound to produce 2,300 units. The company actually used 5,000 pounds that cost $5.10 per pound to produce 2,300 units.

Summerlin Company budgeted 4,500 pounds of material costing $5.00 per pound to produce 2,300 units. The company actually used 5,000 pounds that cost $5.10 per pound to produce 2,300 units. What is the direct materials quantity variance?