Job 397 was recently completed. The following data havebeen recorded on its job costsheet Direct materials.......................................$59,400 Direct labor-hours...........................

Job 397 was recently completed. The following data havebeen recorded on its job costsheet

Direct materials.......................................$59,400

Direct labor-hours....................................1,254DLHs

Direct labor wage rate ..............................$11 perDLH

Number of units completed ......................3,300 units

The company applies manufacturing overhead on theĀ basis of direct labor-hours. The predeterminedoverheadĀ rate is $37 perdirect labor-hour.

Required:

What is the unit product cost that would appear on thejob cost sheet for thisjob?