I could use some help answering this with the attached spreadsheet. I finished parts a through c:

I could use some help answering this with the attached spreadsheet. I finished parts a through c:

I could use some help answering this with the attached spreadsheet. I finished parts a through c:

 

Glassman Company acculated the following data for 2019:

Milling Department manufacturing overhead $484,000
Finishing Department manufacturing overhead $260,000
Machine hours used  
      Milling Department 10,000
     Finishing Deparment 2000
Labor hours used  
      Milling Department 1000
     Finishing Department 1000

 

Assume that manufacturing overhead for Glassman Company above consisted of the following activities and costs:

 

Setup  (1000 setup hours) $288,000
Production scheduling (400 batches) $60,000
Production engineering (60 change orders) $180,000
Supervision (2000 direct labor hours) $56,000
Machine maintenance (12,000 machine hours) $168,000
     Total activity costs $752,000

The following additional data were provided for Job 845:

Direct materials costs $7000
Direct labor cost (5 milling direct labor hours; 35 finishing direct labor house) $1000
Setup hours 5 hours
Production scheduling 1 batch
Machine hours used (25 milling machine hours; 5 finishing machine hours) 30 hours
Product engineering 3 change orders

Problems:

d) Calculate the cost of Job 845 using a machine hour departmental overhead rate for the Milling Department and a direct labor hour overhead rate for the Finishing Department.

Activity cost calculations:
Set up cost
Production scheduling cost
Production engineering cost
Supervision cost
Machine operating cost
include the formula here
a
288,000/1000
60,000/400
180,000/60
56,000/2000
|168,000/12,000
S
288
$
150
3,000
25
14
b Direct materials
$
7,000
Direct labor
Manufacturing overhead cost
Setup hours
Production scheduling
Production engineering
Supervision
Machine Maintenance
1,000
5*288
1*150
3 *3000
1,440
150
9,000
(5+35)*28
1,120
|(25+5)*14
420
Total Job 845 cost
20,130
Direct material
Direct labor cost
Overhead cost
Total Job 845 cost
7,000 Total activities cost 752,000
1,000 Total machine hours used-12,000
1,880 752,000/12,000 $62.67
$
C
30 62.67
9,880
Total Job 845 cost