Home / Questions / Four trucks 1 2 3 and 4 are waiting on a loading dock at XYZ Company that has only a singl...

Four trucks 1 2 3 and 4 are waiting on a loading dock at XYZ Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock Assume the current time

Four trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock. Assume the current time is 1:00 P.M. The times required to unload each truck and the times that the goods they contain are due in the plant are given in the following table.

 

Determine the schedules that result for each of the rules FCFS, SPT, EDD, and CR. In each case compute the mean flow time, average tardiness, and number of tardy jobs.

Jul 28 2020 View more View Less