Firewall Project XT Using the complexity weighting scheme shown in Exercise 53 and the function point complexity weighted table shown below estimate the total function point count Assume

Firewall Project XT. Using the "complexity weighting" scheme shown in Exercise 5.3 and the function point complexity weighted table shown below, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people can work on the project. a. What is the estimated project duration? b. If 20 people are available for the project, what is the estimated project duration? c. If the project must be completed in six months, how many people will be needed for the project? Exercise 5.3
 