Construct a simple block diagram to show these major components of a steam production and power plant system in their correct sequence c A surface condenser is to be designed to condense

Construct a simple block diagram to show these major components of a steam production and power plant system in their correct sequence. (c) A surface condenser is to be designed to condense 150 000 kg hul of dry saturated steam at 0.05 bar. If the overall heat transfer coefficient is 11.5 kW m-K- and the inlet and outlet water temperatures are 14°C and 24°C respectively, calculate the heat transfer surface area required