At the beginning of 2017 Atlantic Yachts enters into a contract to build a luxury yacht for a customer that is expected to take three years to complete. The contract price is $12,000,000. Completion

At the beginning of 2017 Atlantic Yachts enters into a contract to build a luxury yacht for a customer that is expected to take three years to complete. The contract price is $12,000,000. Completion is scheduled for the end of 2019. Atlantic’s year end is December 31. The following is a year by year summary of construction costs incurred and the estimated costs to complete the projects at the end of each year.

2017 2018 2019

Actual costs incurred current year $2,250,000 $6,750,000 $2,325,000

Actual costs incurred prior years -0- $2,250,000 $9,000,000

Cumulative actual costs incurred to date $2,250,000 $9,000,000 $11,325,000

Estimated costs to complete end of year $6,750,000 $2,250,000 -0-

Total Costs $9,000,000 $11,250,000 $11,325,000

Billings $2,100,000 $7,800,000 $2,100,000

Cash Collections $1,500,000 $6,000,000 $4,500,000

Required: Prepare the entries under the completed-contract method for 2017