A job was timed for 60 cycles and had an average of 1.30 minutes per piece The performance rating was 91 percent, and workday allowances are 12 percent Determine each of the following a Observed

A job was timed for 60 cycles and had an average of 1.30 minutes per piece. The performance rating was 91 percent, and workday allowances are 12 percent. Determine each of the following:

a.
 Observed time. (Round your answer to 2 decimal place.)

Observed time            minutes

b. Normal time. (Round your answer to 2 decimal places.)

Normal time            minutes

c.
 Standard time. (Round your answer to 2 decimal places.)

Standard time            minutes