4) The activities, their durations, costs and precedence relationships within a project are described in Table 1 below. Draw a properly annotated project network diagram of this project and determine

4) The activities, their durations, costs and precedence relationships within a project are described in Table 1 below. Draw a properly annotated project network diagram of this project and determine the minimum required time to complete the project and list the critical activities.

Activity

Preceding Activity

Normal Duration

A

-

3

B

-

2

C

-

1

D

A

4

E

A

3

F

B , D

5

G

B , D

3

H

C

4

I

E , F

10

J

H , G

8