3. Accelerate the following project to 30 days. Show the acceleration cost. If a penalty of LE 1500 exists for each days delay beyond 30 days. What would be your plan concerning project time? Explain

3. Accelerate the following project to 30 days. Show the acceleration cost. If a penalty of LE 1500 exists for each days delay beyond 30 days. What would be your plan concerning project time? Explain your answer? Activity Predecessors Duration (days) Normal Crash 12. 9 1 H 6 2 IN IN Cost Slope (LE/day) 2000 2000 1000 2000 4000 5500 D 4 N 8 8 5 7 HD M C 9 7